Design permit issued by Sofia Municipality, Izgrev region
|
20.02.2018
|
EUR 20
|
Contract with Architecture Studio Dual Project EOOD for
full design of the project
|
07.11.2018
|
EUR 28180
|
Contract with PRO CONSULTING EOOD for assessment
of the conformity of the design with the
regulatory requirements as required for the issuance of
the Building Permit
|
17.01.2019
|
EUR 490
|
Building permit No 10 issued by Sofia Municipality,
Izgrev region
|
04.04.2019
|
EUR 7840
|
Contract with PRO CONSULTING EOOD
for independent supervision of the construction works
|
28.11.2019
|
EUR 4140
|
Contract with ELECTROBUILD OOD for the design of
external LV 1 kV cable line for supplying electricity to the
project, including coordination with/consents from
the competent institutions.
|
25.11.2019
|
EUR 3810
|
Contract with HELITRANS STROY AD for execution of
the Structural works up to roof level (excluding roof) and
brick walls
|
29.11.2019
|
EUR 475135
|
Loan agreement with HELITRANS for financing the
final completion of the building at Structural level
|
06.12.2019
|
EUR 153540
|
Contract with Architecture Studio Dual Project EOOD for
supervision by the Designers of all phases of the
investment process
|
14.01.2020
|
EUR 13
|
Certificate (Form No 5) for setting out the construction site
as per the approved project designs and for determination of
the anchor benchmark of the building (site set-out)
|
22.01.2020
|
|
Certificate (Form No 5) for opening the construction site. All required permits from Sofia Municipality available (building permit, use of sidewalks, approved routes of building
machinery to the site, temporary fence, disposal of humus,
earth and debris, temporary electricity and water supply,
temporary sewerage, chemical toilets, etc.).
Commission composed of: Engineer, Supervisor, Designer, Contractor, Project Owner and Chief Expert at
Territory Management, Cadastre and Regulation Department of Izgrev Region
|
28.01.2020
|
|
Advance payment amounting to 20% of the contract price,
transferred in two tranches (on 10.02.2020 and 11.02.2020)
|
|
EUR 95030
|
Certificate (Form No 6) for acceptance of the base ground
and the actual levels reached following the completion of
earthworks. Issued by Project Owner, Supervisor and
Designers of the relevant parts of the project
|
18.03.2020
|
|
Certificate (Form No 2) establishing the conformity of the
levels reached following the completion of the earthworks
with the design levels and with the issued construction
papers. Issued by Consultant (Supervisor, including
Geologist and Surveyor), Project Owner, Designer and
Builder (Contractor)
|
19.03.2020
|
|
Certificate for the removal of partially humidified earth from the base ground pursuant to Order No 2/18.03.2020 given by the Geology Engineer (entered in the Order Book).
Certificate issued by Project Owner and Contractor
|
23.03.2020
|
|
Certificate for canceling the use of a tower crane issued by
Project Owner and Contractor
|
26.03.2020
|
|
Statement of required in-process restructuring of the
reinforcement grid up to 6 meters long above level 0.8 m.
Issued by Contractor, Designer and Project Owner
and approved by Supervisor
|
10.04.2020
|
|
Certificate (Form No 7) confirming the conformity of
formwork and reinforcement of the fundamental slab and
of the column footings with the design requirements. Issued by Supervisor, Designer and Builder
|
13.04.2020
|
|
Concrete pour – fundamental slab
|
14.04.2020
|
|
Statement (Form No 3) confirming the conformity of the
project with the issued construction papers and with the
Detailed Layout Plan, issued by the competent official at
Sofia Municipality, Izgrev region (Head of Infrastructure and Spatial Planning Department)
|
08.05.2020
|
|
Report on increasing the number, the anchoring length and
the depth of the piles due to heavy precipitation and
for safety reasons. Issued by Contractor, Supervisor and
Project Owner.
|
18.05.2020
|
|
Report on the installation of casing pipes for piles following
the discovery of an old cesspit, issued by Contractor and
Project Owner
|
21.05.2020
|
|
Addendum No 1 (to the Construction Contract of
29 November 2019) concerning additional construction and
installation works in accordance with the Explanations to
Addendum No 1
|
27.052020
|
|
Payment pursuant to Annex 1, point 1 of Contract К31/2019 with PRO CONSULTING EOOD — 10 % upon the
issuance of Certificate (Form No 3) confirming the
conformity of the foundations with the Detailed Layout Plan
|
|
EUR 390
|
Certificate 1 (Form No 19) of completed Structural Works
|
|
EUR 144825
|
Concrete pour – slab at level 0.08 (formwork and
reinforcement approved by the Structural Designer as per
Order dd. 30.06.2020)
|
1.07.2020
|
|
Concrete pour – slab at level 3.42 (formwork and
reinforcement approved by the Structural Designer as per
Order dd. 18.08.2020)
|
19.08.2020
|
|
Concrete pour – slab at level 6.32 (formwork and
reinforcement approved by the Structural Designer as per
Order dd. 28.09.2020)
|
30.09.2020
|
|
Certificate 2 (Form No 19) of completed Structural Works
|
04.09.2020
|
EUR 88270
|