PROJECT NAME: Residential building, including gallery, store and underground parking
lot in Regulated Land Plot (UPI) III-346, Quarter 20, Locality East-South
as per the plan of Sofia, property ID 68134.800.5356 – Structural completion

PROJECT TIMELINE:

Design permit issued by Sofia Municipality, Izgrev region

20.02.2018

EUR 20

Contract with Architecture Studio Dual Project EOOD for
full design of the project

07.11.2018

EUR 28180

Contract with PRO CONSULTING EOOD for assessment
of the conformity of the design with the
regulatory requirements as required for the issuance of
the Building Permit

17.01.2019

EUR 490

Building permit No 10 issued by Sofia Municipality,
Izgrev region

04.04.2019

EUR 7840

Contract with PRO CONSULTING EOOD
for independent supervision of the construction works

28.11.2019

EUR 4140

Contract with ELECTROBUILD OOD for the design of
external LV 1 kV cable line for supplying electricity to the
project, including coordination with/consents from
the competent institutions.

25.11.2019

EUR 3810

Contract with HELITRANS STROY AD for execution of
the Structural works up to roof level (excluding roof) and
brick walls

29.11.2019

EUR 475135

Loan agreement with HELITRANS for financing the
final completion of the building at Structural level

06.12.2019

EUR 153540

Contract with Architecture Studio Dual Project EOOD for
supervision by the Designers of all phases of the
investment process

14.01.2020

EUR 13

Certificate (Form No 5) for setting out the construction site
as per the approved project designs and for determination of
the anchor benchmark of the building (site set-out)

22.01.2020

Certificate (Form No 5) for opening the construction site. All required permits from Sofia Municipality available (building permit, use of sidewalks, approved routes of building
machinery to the site, temporary fence, disposal of humus,
earth and debris, temporary electricity and water supply,
temporary sewerage, chemical toilets, etc.).
Commission composed of: Engineer, Supervisor, Designer, Contractor, Project Owner and Chief Expert at
Territory Management, Cadastre and Regulation Department of Izgrev Region

28.01.2020

Advance payment amounting to 20% of the contract price,
transferred in two tranches (on 10.02.2020 and 11.02.2020)

EUR 95030

Certificate (Form No 6) for acceptance of the base ground
and the actual levels reached following the completion of
earthworks. Issued by Project Owner, Supervisor and
Designers of the relevant parts of the project

18.03.2020

Certificate (Form No 2) establishing the conformity of the
levels reached following the completion of the earthworks
with the design levels and with the issued construction
papers. Issued by Consultant (Supervisor, including
Geologist and Surveyor), Project Owner, Designer and
Builder (Contractor)

19.03.2020

Certificate for the removal of partially humidified earth from the base ground pursuant to Order No 2/18.03.2020 given by the Geology Engineer (entered in the Order Book).
Certificate issued by Project Owner and Contractor

23.03.2020

Certificate for canceling the use of a tower crane issued by
Project Owner and Contractor

26.03.2020

Statement of required in-process restructuring of the
reinforcement grid up to 6 meters long above level 0.8 m.
Issued by Contractor, Designer and Project Owner
and approved by Supervisor

10.04.2020

Certificate (Form No 7) confirming the conformity of
formwork and reinforcement of the fundamental slab and
of the column footings with the design requirements. Issued by Supervisor, Designer and Builder

13.04.2020

Concrete pour – fundamental slab

14.04.2020

Statement (Form No 3) confirming the conformity of the
project with the issued construction papers and with the
Detailed Layout Plan, issued by the competent official at
Sofia Municipality, Izgrev region (Head of Infrastructure and Spatial Planning Department)

08.05.2020

Report on increasing the number, the anchoring length and
the depth of the piles due to heavy precipitation and
for safety reasons. Issued by Contractor, Supervisor and
Project Owner.

18.05.2020

Report on the installation of casing pipes for piles following
the discovery of an old cesspit, issued by Contractor and
Project Owner

21.05.2020

Addendum No 1 (to the Construction Contract of
29 November 2019) concerning additional construction and
installation works in accordance with the Explanations to
Addendum No 1

27.052020

Payment pursuant to Annex 1, point 1 of Contract К31/2019 with PRO CONSULTING EOOD — 10 % upon the
issuance of Certificate (Form No 3) confirming the
conformity of the foundations with the Detailed Layout Plan

EUR 390

Certificate 1 (Form No 19) of completed Structural Works

EUR 144825

Concrete pour – slab at level 0.08 (formwork and
reinforcement approved by the Structural Designer as per
Order dd. 30.06.2020)

1.07.2020

Concrete pour – slab at level 3.42 (formwork and
reinforcement approved by the Structural Designer as per
Order dd. 18.08.2020)

19.08.2020

Concrete pour – slab at level 6.32 (formwork and
reinforcement approved by the Structural Designer as per
Order dd. 28.09.2020)

30.09.2020

Certificate 2 (Form No 19) of completed Structural Works

04.09.2020

EUR 88270

 

BROTHERHOOD CENTRE

Donations

Your financial contribution to the construction of the Brotherhood Centre will be highly appreciated. Please send your donation to the bank account of White Brotherhood Society or via Paypal:

Bank Account:

Account name:
ОБЩЕСТВО БЯЛО БРАТСТВО (BYALO BRATSTVO SOCIETY)
IBAN: BG43UNCR96601060704509
BIC: UNCRBGSF 

Reason for payment: For the new Brotherhood Centre

Paypal link for donating directly through the Internet: 




Reason for payment: For the new Brotherhood Centre

Thank you!

Brotherhood Groups